Accurate Lien

Louisiana Lien Laws

Lien laws vary significantly across states, reflecting the diverse legal landscapes and economic conditions throughout the U.S. These laws govern the rights of creditors to claim an interest in property to secure payment for debts. For instance, some states have specific statutes that provide detailed processes for mechanics’ liens, allowing contractors and suppliers to enforce claims for unpaid work or materials on construction projects. In contrast, other states might have more streamlined or less detailed regulations. 

Quicklinks

This link is under construction​

This link is under construction​

This link is under construction​

This link is under construction​

This link is under construction​

Supplier – Preliminary notice requirements to file mechanic lien
If hired by a subcontractor, the notice must be sent within 75 days of the last day of the month of furnishing labor and/or materials. Equipment Lessors must deliver a notice to the owner and prime within 30 days of furnishing equipment. A professional sub-consultant, architect, engineer or surveyor must give notice to the owner within 30 days of first furnishing.
Supplier – Mechanic Lien
Notice of non-payment must be delivered to the owner at least ten days prior to filing a lien. Subcontractor or suppliers claim of lien must be filed within thirty days from the filing of a notice of termination; however, if a notice of contact was not timely filed the lien period is extended to 60 day from substantial completion of the entire work or abandonment by the owner.
Subcontractor – Preliminary notice requirements to file mechanic lien
No preliminary notice is required.
Subcontractor – Mechanic Lien
Subcontractor or suppliers claim of lien must be filed within thirty days from the filing of a notice of termination; however, if a notice of contact was not timely filed the lien period is extended to 60 days from substantial completion of the entire work or abandonment by the owner.
General Contractor – Preliminary notice requirements to file mechanic lien
Notice of Contract must be recorded before work begins if contract more than $25,000.00.
General Contractor – Mechanic Lien
Liens must be filed within 60 days from substantial completion of the entire work.
Timeframe to foreclose lien
Liens must be foreclosed upon within 1 year of recording of lien.
Construction participants not covered by lien law
Material suppliers whose customers are not the contractor or a subcontractor are not protected by Louisiana lien law.
Cost and damages not allowed in lien claim
Items that typically are not allowed in a lien claim are punitive damages, attorney’s fees other than as provided by statute, and materials not incorporated in or consumed on the project.