Kansas Lien Laws

Lien laws vary significantly across states, reflecting the diverse legal landscapes and economic conditions throughout the U.S. These laws govern the rights of creditors to claim an interest in property to secure payment for debts. For instance, some states have specific statutes that provide detailed processes for mechanics’ liens, allowing contractors and suppliers to enforce claims for unpaid work or materials on construction projects. In contrast, other states might have more streamlined or less detailed regulations. 

Quicklinks

This link is under construction​

This link is under construction​

This link is under construction​

This link is under construction​

This link is under construction​

Supplier – Preliminary notice requirements to file mechanic lien
A warning statement must be given to the property owner if a subcontractor and/or supplier wishes to claim a lien on pre-existing residential property.
Supplier – Mechanic Lien
Lien must be filed within 3 months of last providing materials or labor. In order to extend the lien timeframe the notice of extension must be filed within 3 months which will extend lien timeframe to within 5 months from last providing materials or labor.
Subcontractor – Preliminary notice requirements to file mechanic lien
A warning statement must be given to the property owner if a subcontractor and/or supplier wishes to claim a lien on pre-existing residential property.
Subcontractor – Mechanic Lien
Lien must be filed within 3 months of last providing materials or labor. In order to extend the lien timeframe the notice of extension must be filed within 3 months which will extend lien timeframe to within 5 months from last providing materials or labor.
General Contractor – Preliminary notice requirements to file mechanic lien
On new residential property, the contractor must file a Notice to Intent to Perform – this is not a preliminary notice document.
General Contractor – Mechanic Lien
Lien must be filed within 4 months of last providing materials or labor, unless a one-month extension is filed and served.
Timeframe to foreclose lien
Action to enforce must be commenced within 1 year of recording of lien.
Construction participants not covered by lien law
subcontractors of subcontractors, a supplier of a supplier and a supplier to a sub subcontractor.
Cost and damages not allowed in lien claim
There is no allowance for attorney’s fees, costs or other charges.